Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for inter-collegiate basketball games, expanded office space, classrooms, and intramural facilities that would have to be undertaken before beginning construction are shown below.
Activity Description Immediate predecessor Time(weeks)
A Survey building site ---- 6
B Develop Initial design ---- 8
C Obtain board approval A,B 12
D Select architect C 4
E Establish budget C 6
F Finalize design D,E 15
G Obtain financing E 12
H Hire contractorB F,G 8
Draw a project network, and develop the activity schedule for each activity. • What is the expected completion time? • What is the critical path?