Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for inter-collegiate basketball games, expanded office space, classrooms, and intramural facilities that would have to be undertaken before beginning construction are shown below.

Activity Description Immediate predecessor Time(weeks)
A Survey building site ---- 6 B Develop Initial design ---- 8 C Obtain board approval A,B 12 D Select architect C 4 E Establish budget C 6 F Finalize design D,E 15 G Obtain financing E 12 H Hire contractorB F,G 8

Draw a project network, and develop the activity schedule for each activity. • What is the expected completion time? • What is the critical path?

flag
9 
Problem 8 on page 437 of "An Introduction to Management Science" by Anderson, Sweeney, Williams, and Martin? This isn't a research level math question (please see the FAQ). – Henry Cohn Mar 21 2011 at 4:38
9 
Sujit, if you type the first sentence of your homework question into Google you would find that someone has already asked the question on the website justanswer.com, and on that site you can pay people to do your work for you instead of having to think for yourself. – KConrad Mar 21 2011 at 4:52

closed as off topic by Gerry Myerson, Daniel Litt, Steve Huntsman, Will Jagy, Andres Caicedo Mar 21 2011 at 5:04

Browse other questions tagged or ask your own question.